15 — Overall Status: Replatforming Program (v3)

Scope: Live status of the Replatforming program — structured by the Phase → Milestone → Increment → Epic delivery framework (doc 19).

Validated: 2026-06-30 — against live GCP (platform-dev-p01, europe-north1), GitHub (PricerAB org), Jira (project = PLT), and the evo-dtoflow-protos central-documentation branch.

Status legend: ✅ Closed = done · 🟢 Live = deployed · 🟡 In Progress / Test / Selected / Ready for Deploy = active · 🔴 Blocked = gated · 🔵 Backlog = not started


1. Program Structure

This doc uses the Phase → Milestone → Increment → Epic delivery hierarchy defined in doc 19. See that doc for the full explanation of each level.

---
config:
    layout: elk
---
flowchart LR
    P0["P0: Prove It<br/>Zero label risk"] --> M1["M1: Platform<br/>Foundation<br/>🟡"]
    P0 --> M2["M2: Shadow Mode<br/>Validation<br/>🟡"]
    M1 --> M2
    M2 --> M3["M3: First Tenant<br/>Go-Live<br/>🔴"]
    M3 --> M4["M4: Production<br/>Hardening<br/>🔵"]
    M4 --> LIVE["First real<br/>tenant live"]
    M4 --> M5["M5: Feature<br/>Parity<br/>🔵"]
    M5 --> M6["M6: Full<br/>Migration<br/>🔵"]

    classDef active fill:#F9E79F,stroke:#D4AC0D,color:#1a1a1a
    classDef gated fill:#F5B7B1,stroke:#C0392B,color:#1a1a1a
    classDef future fill:#E5E7EB,stroke:#9CA3AF,color:#1a1a1a
    class M1,M2 active
    class M3 gated
    class M4,M5,M6 future

Every epic carries a Capability tag[C1] through [C5] — for architecture-level filtering. These are reference tags, not delivery levels. See doc 19 §6 for definitions.


2. The Milestones

Milestone Phase Goal Increments Gate Target
M1: Platform Foundation P0 Core infrastructure live and certified 2 All Increment demos pass W31 (Aug 2)
M2: Shadow Mode Validation P0 Cloud pipeline runs in parallel with edge. Zero label risk. 4 24h parity across three tenants confirmed W34 (Aug 23)
M3: First Tenant Go-Live P1 Item and link API traffic cut over to cloud 3 One real tenant live for basic flows W38 (Sep 20)
M4: Production Hardening P1 Monitoring, load testing, DR, runbooks 3 All ops gates passed W44 (Nov 1)
M5: Feature Parity P2 Timed updates, ECC sync, autoscaling, SLAs TBD Feature parity with R3Server achieved 2027
M6: Full Migration P2 All tenants migrated TBD All tenants on cloud 2027

Current State

---
config:
    layout: elk
---
flowchart LR
    M1["M1: Platform<br/>Foundation<br/>🟡 Active"] --> M2["M2: Shadow Mode<br/>Validation<br/>🟡 Active"]
    M2 --> M3["M3: First Tenant<br/>Go-Live<br/>🔴 Gated"]
    M3 --> M4["M4: Production<br/>Hardening<br/>🔵 Not started"]
    M4 --> LIVE["First real<br/>tenant live"]
    M4 --> M5["M5: Feature<br/>Parity<br/>🔵 Not started"]

    classDef active fill:#F9E79F,stroke:#D4AC0D,color:#1a1a1a
    classDef gated fill:#F5B7B1,stroke:#C0392B,color:#1a1a1a
    classDef future fill:#E5E7EB,stroke:#9CA3AF,color:#1a1a1a
    class M1,M2 active
    class M3 gated
    class M4,M5 future

M1 and M2 are active. M3 is gated by two blocked epics (PLT-2651, PLT-2378). M4 and M5 are entirely in backlog.


3. Phase 0: M1 — Platform Foundation

Inc Name Demo Status Target
1.1 Core Event Routing Dummy DTO → CQS → Cloud Run queue 🟡 Active W29 (Jul 19)
1.2 Internal Comm & Security R3Server ↔ cloud CQS bridge + PSC + PROD certification 🟡 Active W31 (Aug 2)

Increment 1.1: Core Event Routing

Epic Cap Status Assignee Summary
— (infra) [C1] 🟢 Live Spanner dtoflow (29 tables, 1000 PU), Pub/Sub (32 topics), gRPC clients (Java + Node), GCS/LFS, dtoflow-spanner, dtoflow-lfs, GKE platform
PLT-2294 [C1] ✅ Closed Bart De Boer ID & alias validation in DTOflow servers
PLT-169 [C1] 🟡 In Progress Johan Ekman ChangeQueueService — subscription-based event fan-out
PLT-2792 [C1] 🟡 In Progress Bart De Boer Services own their CQS queues
PLT-2478 [C1] 🟡 In Progress Sreekanth S. Uppara Pricer Server ↔ CQS / DTOflow integration design

Increment 1.2: Internal Comm & Security

Epic Cap Status Assignee Summary
PLT-1870 [C4] 🟡 Test Daniel Pettersson CQS client in R3Server — edge-side work dispatch
PLT-2336 [C1] 🟡 In Progress Sreekanth S. Uppara DTOflow accessible via Private Service Connect
PLT-2118 [C1] 🟡 Test Bart De Boer DTOflow PROD-ready certification for Task & Scenario

4. Phase 0: M2 — Shadow Mode Validation

Inc Name Demo Status Target
2.1 Core Data Tap Price update in R3 → all DTOs in Spanner 🟡 Active W30 (Jul 26)
2.2 Shadow Mode Completion Item change → cloud render → transmit dropped 🟡 Active W32 (Aug 9)
2.3 API Parity Validation Extend API dev to cover Basic Functionality 🔵 Not started W33 (Aug 16)
2.4 Routing Per-API-path routing at ingress 🔵 Not started W34 (Aug 23)

Increment 2.1: Core Data Tap

This Increment has 8 epics (above the 2-4 target) because all export pipes share one dependency chain and one demo: "price update in R3 → all DTOs appear in Spanner." The pipes are individually small — most are 1-2 story points — and can be built in parallel once the first pipe (PLT-2483) proves the export mechanism.

Epic Cap Status Assignee Summary
PLT-2353 [C4] 🟡 In Progress Bart De Boer Pricer Server config export to DTOflow
PLT-2483 [C4] 🟡 Ready for Deploy Johan Ekman storeitemvalues export — real-time item data pipe
PLT-2496 [C4] 🟡 Ready for Deploy Unassigned Link export — real-time link data pipe
PLT-2494 [C4] 🟡 In Progress Johan Ekman ECC params / images / models export
PLT-2495 [C4] 🟡 Selected Unassigned ECC fonts export
PLT-2492 [C4] 🟡 Selected Unassigned ESL Status DTO export
PLT-2488 [C4] 🟡 Selected Unassigned itemproperties export
PLT-2714 [C4] 🟡 Selected Unassigned itemproperties startup export

Increment 2.2: Shadow Mode Completion

Epic Cap Status Assignee Summary
PLT-2497 [C4] ✅ Closed Unassigned consume-ignore-linked mode — label transmit safely dropped
PLT-2354 [C4] 🟡 In Progress Daniel Pettersson Shadow Mode orchestration — parallel cloud pipeline
PLT-2359 [C3] 🟡 In Progress Bart De Boer ECC Rendering Support — added to Phase 0 from M5

Increment 2.3: API Parity Validation

Epic Cap Status Assignee Summary
PLT-2966 [C2] 🔵 Backlog Unassigned API Parity Validation — new epic for Inc 2.3 gate
PLT-2357 [C3] 🟡 Selected Unassigned Linked Item APIs — Items
PLT-2358 [C3] 🟡 Selected Unassigned Linked Item APIs — Devices

Increment 2.4: Routing

Epic Cap Status Assignee Summary
PLT-2101 [C1] 🟡 Selected Saikiran Katta Per-API-path routing — the mechanism that makes migration incremental

5. Phase 1 Preview: M3 & M4

PLT-2357 and PLT-2358 appear in both M2 Inc 2.3 (Phase 0: API parity validation) and M3 (Phase 1: full Linked Item API implementation). Phase 0 validates basic parity; Phase 1 completes the full feature set. Same pattern as PLT-2359 (used in Inc 2.2 for Phase 0 ECC rendering support, full scope in M5).

M3: First Tenant Go-Live

Epic Cap Status Assignee Summary
PLT-2651 [C2] 🔴 Blocked Unassigned Item property validation — single clearest gate on item-driven migration
PLT-2378 [C2] 🔴 Blocked Unassigned Item Patch APIs — Core (gates Plaza Mobile + Central-Manager)
PLT-2274 [C2] 🔴 Blocked Daniel Pettersson SIC Support — items findable by Store Item Code
PLT-2598 [C2] ✅ Closed Unassigned Initial Bulk Item Load (scope-out)
PLT-2773 [C3] ✅ Closed Johan Ekman ECC Link Projector
PLT-2771 [C3] ✅ Closed Unassigned ESL Image Merger
PLT-2484 [C3] 🟡 In Progress Bart De Boer Link v1 DTO refactor
PLT-2357 [C3] 🟡 Selected Unassigned Linked Item APIs — Items
PLT-2358 [C3] 🟡 Selected Unassigned Linked Item APIs — Devices
PLT-2577 [C4] ✅ Closed Unassigned ESL registration in cloud

M4: Production Hardening

Epic Cap Status Assignee Summary
PLT-2600 [C3] 🔵 Backlog Unassigned Studio Services Prod-Readiness certification
PLT-2601 [C5] 🔵 Backlog Cristian Deaconeasa First Tenant Selection — gate decision for Phase 1 scope
PLT-2572 [C5] 🔵 Backlog Unassigned Store Onboarding — repeatable store provisioning
PLT-2575 [C5] 🔵 Backlog Unassigned Store DTO Schema — store metadata in cloud
PLT-2578 [C5] 🔵 Backlog Unassigned Tenant Isolation Validation
PLT-2576 [C5] 🔵 Backlog Unassigned Performance & Load Testing — 652M items scale
PLT-2579 [C5] 🔵 Backlog Unassigned Monitoring & Dashboards
PLT-2580 [C5] 🔵 Backlog Unassigned Disaster Recovery — backups, restore, DR drills
PLT-2599 [C5] 🔵 Backlog Unassigned Cutover & Rollback Runbook
PLT-2581 [C5] 🔵 Backlog Unassigned Operational Runbooks
PLT-2430 [C5] 🔵 Backlog Unassigned Integration Tests Delivery 1 — automated E2E suite

6. Phase 2: M5 — Feature Parity

All epics in backlog. PLT-2359 has early progress (Bart De Boer building ECC parity in parallel).

Epic Cap Status Assignee Summary
PLT-171 [C1] 🟡 Selected Unassigned SLA & trackingId support
PLT-170 [C1] 🔵 Backlog Unassigned Write Protection — Auth0 JWT-based access control
PLT-2444 [C1] 🔵 Backlog Unassigned Status Reporting
PLT-2369 [C1] 🔵 Backlog Unassigned Auto-scaling
PLT-2350 [C2] 🔵 Backlog Unassigned Timed Item Updates
PLT-2351 [C2] 🔵 Backlog Unassigned Item Ingest Status — Extended
PLT-2352 [C2] 🔵 Backlog Unassigned Item Ingest Status — Advanced
PLT-2436 [C2] 🔵 Backlog Unassigned Item / Link via PFI
PLT-2359 [C3] 🟡 In Progress Bart De Boer ECC Links & Rendering — building early (Phase 2 scope)
PLT-2361 [C3] 🔵 Backlog Unassigned Segment Labels
PLT-2360 [C3] 🔵 Backlog Unassigned Unified Linking API
PLT-2363 [C3] 🔵 Backlog Unassigned Auto Unlink
PLT-2573 [C4] ✅ Closed Unassigned ECC Sync push (scope-out)
PLT-2574 [C4] ✅ Closed Unassigned Transmission service integration (scope-out — won't do)
PLT-2355 [C4] 🟡 Selected Bart De Boer Label Status APIs
PLT-2356 [C4] 🔵 Backlog Unassigned Item Flash APIs — stays on R3Server edge
PLT-2362 [C4] 🔵 Backlog Unassigned GeoPos Support
PLT-2428 [C5] 🔵 Backlog Unassigned Subscription System
PLT-2440 [C5] 🔵 Backlog Unassigned Webhook Events

Note on PLT-2359: Marked In Progress in M5 (Phase 2). Bart De Boer is building ECC parity early. The first real tenant (M3) uses Studio rendering only. This is early progress on a Phase 2 capability — not Phase 2 work blocking Phase 1.

M6: Full Migration

Not yet scoped. Will be defined when M5 is underway.


7. Infrastructure Health

All services deployed in GCP project platform-dev-p01, region europe-north1.

Component Details Status
Spanner Instance dtoflow, 1000 PU, 29 DTO tables + item-registry (1 table) 🟢 Healthy
Pub/Sub 32 topics (dtoflow-changes-*, DLQ, sync, item-registry-requests) 🟢 Healthy
Cloud Run 21 services deployed 🟢 All live
GKE Cluster platform — runs ChangeQueueService 🟢 Healthy
GCS / LFS dtoflow-lfs — content-addressed SHA-256 storage 🟢 Healthy
Apigee API gateway — front door to Cloud Run 🟡 PSC setup in progress (PLT-2336)
Ingress PCS ingress-nginx — per-API-path routing not started (PLT-2101) 🟡 Selected

Cloud Run Service Inventory

Domain Services
Item item-registry-api, item-registry
Link link-registry, link-bfg, link-storeasset-bfg
Studio Rendering studio-link-evaluator, studio-renderer, studio-design-library, studio-scenario-library
ECC Rendering ecc-link-projector, ecc-renderer, esl-image-merger
Edge Bridge dtoflow-transmission
Actions actions-executor, actions-library
Operations delivery-sync-service, delivery-dashboard, dtoflow-changequeue-dashboard, migration-helper
Storage dtoflow-spanner, dtoflow-lfs

8. Executive Summary

The DTOflow cloud platform is largely live. 21 Cloud Run services deployed. Link processing, rendering, and transmission operational end-to-end. The primary delivery risk is concentrated in M3 (First Tenant Go-Live), where two blocked epics — PLT-2651 (Item property validation) and PLT-2378 (Item Patch APIs) — gate all item-driven flows.

Program at a Glance

Milestone Status Key Signal Target
M1: Platform Foundation 🟡 Active CQS (1.1) In Progress; Internal Comm (1.2) in Test W31 (Aug 2)
M2: Shadow Mode Validation 🟡 Active 2 data pipes Ready for Deploy (2.1); Shadow orchestration In Progress (2.2) W34 (Aug 23)
M3: First Tenant Go-Live 🔴 Gated 2 blocked & unassigned epics — highest-priority action in the program W38 (Sep 20)
M4: Production Hardening 🔵 Not started All 11 epics in Backlog W44 (Nov 1)
M5: Feature Parity 🔵 Not started 19 epics in Backlog; one with early progress 2027

Key End-to-End Flows

Flow Status Detail
Link Creation → Render → Transmit 🟢 Live link-registry → evaluator + renderer (parallel) → merger → dtoflow-transmission → R3Server → ESL
Item Price Change → Render 🟡 Partially ready Evaluator + renderer chain operational; gated by item property validation (PLT-2651)
Item Deletion 🔴 Not built Path not yet implemented

9. Risks & Immediate Actions

Critical

Risk Epic Severity Action
Item property validation blocked PLT-2651 ([C2]) 🔴 Critical Unblock. 4 of 5 item pipeline services built. This is the single clearest gate.
Item Patch APIs unassigned PLT-2378 ([C2]) 🔴 Critical Assign owner. Gates Plaza Mobile + Central-Manager cutover.

High Priority

Risk Severity Action
Shadow Mode sub-tasks unassigned — PLT-2495, 2492, 2488, 2714 need owners 🟡 High Assign before next sprint
Bart De Boer owns 4+ critical epics across M1, M2, M3, M5 🟡 High Spread ownership
API routing not started — PLT-2101, Saikiran on vacation 🟡 Medium Plan handover
First tenant selection in Backlog — PLT-2601 🟡 Medium Drive criteria → decision
Review bottleneck — 6+ items waiting for Johan Ekman 🟡 Medium Distribute review load
Ops readiness entirely in Backlog — M4 has 11 epics, none started 🟡 Medium Begin sequencing before tenant cutover

10. What's Next

In priority order:

  1. Unblock PLT-2651 (Item property validation) — the single clearest gate.
  2. Assign owner to PLT-2378 (Item Patch APIs) — gates both consumer API cutovers.
  3. Land PLT-2483 (storeitemvalues export) — Ready for Deploy, completes Inc 2.1.
  4. Finish PLT-1870 (CQS client in R3Server) — in Test, completes Inc 1.2.
  5. Certify PLT-2118 (DTOflow PROD-ready) — completes Inc 1.2.
  6. Drive PLT-2601 (First Tenant Selection) — from Backlog to decision, unlocks M3.

Refresh sources: - GCP: gcloud run services list --region=europe-north1 --project=platform-dev-p01 - Jira: project = PLT AND issuetype = Epic AND labels in ("replatforming-phase-0","replatforming-phase-1","replatforming-phase-2") ORDER BY status ASC