20 — Phase 0 Effort Estimation Analysis

Scope: Analysis of time tracking and effort estimates for all 22 Phase 0 epics across M1 (Platform Foundation) and M2 (Shadow Mode Validation). Identifies gaps between current estimates and the late-August 2026 deadline (Week 34).

Deadline: Late August 2026 (~23 August / Week 34). Today: 1 July 2026. Remaining: ~38 working days (7.6 weeks) assuming full attendance. Reduce by 5 days per engineer-week of vacation — July–August is peak holiday season in Sweden.

Data pulled: 2026-07-01 — live Jira (project = PLT, all Phase 0 epics), including subtask breakdowns and aggregated time tracking.


1. Raw Data — All Phase 0 Epics

Epic Inc Summary Status Assignee Orig Est Remaining Spent Subtasks
PLT-2294 1.1 ID & alias validation ✅ Closed Bart De Boer 2w 2w 0
PLT-169 1.1 ChangeQueueService 🟡 In Progress Johan Ekman 5w 1w 4w 0
PLT-2792 1.1 Services own CQS queues 🟡 In Progress Bart De Boer Not set Not set Not set 9
PLT-2478 1.1 PS ↔ CQS/DTOflow design 🟡 In Progress Sreekanth S. Not set Not set Not set 0
PLT-1870 1.2 CQS client in R3Server 🟡 Test Daniel P. Not set Not set Not set 0
PLT-2336 1.2 DTOflow PSC accessibility 🟡 In Progress Sreekanth S. 1w 1w 0
PLT-2118 1.2 DTOflow PROD-ready cert 🟡 Test Bart De Boer 5w 2d 4w 3d 1
PLT-2353 2.1 Pricer Server config export 🟡 In Progress Bart De Boer 1w 1d 1w 1d 0
PLT-2483 2.1 storeitemvalues export 🟡 Ready Johan Ekman Not set Not set Not set 0
PLT-2496 2.1 Link export 🟡 Ready Unassigned Not set Not set Not set 1
PLT-2494 2.1 ECC params/images/models 🟡 In Progress Johan Ekman Not set Not set Not set 0
PLT-2495 2.1 ECC fonts export 🟡 Selected Unassigned Not set Not set Not set 0
PLT-2492 2.1 ESL Status DTO export 🟡 In Progress Bart De Boer Not set Not set Not set 3
PLT-2488 2.1 itemproperties export 🟡 Code Review Unassigned Not set Not set Not set 2
PLT-2714 2.1 itemproperties startup 🟡 Selected Unassigned Not set Not set Not set 0
PLT-2497 2.2 Consume-ignore-linked mode ✅ Closed Unassigned Not set Not set Not set 0
PLT-2354 2.2 Shadow Mode orchestration 🟡 In Progress Daniel P. 1w 2d 1w 2d 0
PLT-2359 2.2 ECC Rendering Support 🟡 In Progress Bart De Boer Not set Not set Not set 0
PLT-2966 2.3 API Parity Validation 🔵 Backlog Unassigned Not set Not set Not set 0
PLT-2357 2.3 Linked Item APIs — Items 🟡 Selected Unassigned Not set Not set Not set 0
PLT-2358 2.3 Linked Item APIs — Devices 🟡 Selected Unassigned Not set Not set Not set 0
PLT-2101 2.4 Per-API-path routing 🟡 Selected Saikiran K. 3d 2d 1d 0

Aggregate time tracking (sum of epic + all subtask estimates per Jira): PLT-169 has 20w aggregate original (4 subtasks at 5w each), 4w remaining. PLT-2118 has 20w aggregate original, 2d remaining. All other aggregates match the epic-level figure or are not set.


2. Headline Finding: 14 of 22 Epics Have No Estimates

Has Estimate Count Epics
Estimated 7 PLT-2294, 169, 2336, 2101, 2118, 2353, 2354
Not set 15 PLT-2792, 2478, 1870, 2483, 2496, 2494, 2495, 2492, 2488, 2714, 2497, 2359, 2966, 2357, 2358

Of the 11 without estimates: - 2 are closed or Ready for Deploy (PLT-2497, 2483, 2496) — low risk, mostly done - 2 are in Code Review (PLT-2488) or Selected (PLT-2714, 2357, 2358) — implementation mostly done, review or assignment remaining - 2 are In Progress, unestimated (PLT-2792 with 9 subtasks, PLT-2478) — high risk - 2 are In Progress, unestimated, similar to estimated peers (PLT-2494, 2492) — medium risk - 1 is in Test (PLT-1870) — low risk, mostly done

Without estimates, sprint planning is blind. Team capacity cannot be allocated and the lead cannot answer "will Phase 0 close by Week 34" with data.


3. PLT-2354: The Single Most Critical Estimate Error

Current estimate: 1w 2d (7 working days)

Why this is wrong: Shadow Mode orchestration is not a feature — it is the integration of every Phase 0 deliverable into one coordinated system. It must:

  1. Activate parallel execution across all 8 data pipes simultaneously
  2. Capture and compare every dtoflow-transmission drop against edge output
  3. Validate 100% rendered-image parity across all three Shadow Mode tenants
  4. Run continuously for 24+ hours without intervention
  5. Handle failure modes: pipe stalls, image mismatches, config drift, event ordering

Comparable epics for scale reference:

Epic What it built Actual effort
PLT-169 ChangeQueueService — single service, single domain 5w
PLT-2118 DTOflow PROD-ready — single domain certification 5w

PLT-2354 must coordinate all domains across all pipes. It is not a 7-day task. A realistic estimate:

Phase Activity Duration
Skeleton Connect orchestrator to all pipes, verify each pipe responds 1w
Parallel run Run all pipes simultaneously, fix ordering/timing issues 1.5w
Parity validation Compare images, fix rendering diffs 1.5w
Multi-tenant Repeat on Evo-Se and Application-Stage 1w
Total ~5w (25 working days)

Corrected estimate: 5w, not 1w 2d. Delta: +3.5w (+18 days).

This correction alone consumes most of the remaining 38 working days.


4. Suggested Estimates for Unestimated Epics

M1 Inc 1.1 — Core Event Routing

Epic Current Suggested Rationale
PLT-2792 Not set 2w 9 subtasks (PLT-2793–2801). Services managing their own CQS queues is configuration + testing work across multiple services. Bart De Boer.
PLT-2478 Not set 1.5w PS ↔ CQS/DTOflow integration design. Sreekanth S.

M1 Inc 1.2 — Internal Comm & Security

Epic Current Suggested Rationale
PLT-1870 Not set 3d remaining In Test. Implementation done. Remaining work is test pass + bug fixes.
PLT-2336 1w 1w remaining DTOflow PSC accessibility. Already In Progress, Sreekanth S.
PLT-2118 5w 2d remaining DTOflow PROD-ready. In Test, Bart De Boer. Aggregate 20w original, 2d remaining.

M2 Inc 2.1 — Core Data Tap

Epic Current Suggested Rationale
PLT-2483 Not set 1d remaining Ready for Deploy. Done or nearly done.
PLT-2496 Not set 1d remaining Ready for Deploy. Done or nearly done. Also unassigned — needs owner.
PLT-2494 Not set 3d remaining In Progress, Johan Ekman. ECC params/images/models. Similar pattern to PLT-2483.
PLT-2495 Not set 2d Selected, unassigned. ECC fonts export only — narrow scope. Needs owner.
PLT-2492 Not set 3d remaining In Progress, Bart De Boer. 3 subtasks. ESL Status DTO.
PLT-2488 Not set 1d remaining Code Review. Implementation done. Review + merge only. Unassigned — needs reviewer assigned.
PLT-2714 Not set 1d remaining Code Review. Same as PLT-2488.

M2 Inc 2.3 — API Parity Validation

Epic Current Suggested Rationale
PLT-2966 Not set 2w New epic for Inc 2.3 gate. API parity validation across item, link, and rendering APIs. Needs scoping.
PLT-2357 Not set 1w Linked Item APIs — Items. Selected, unassigned.
PLT-2358 Not set 1w Linked Item APIs — Devices. Selected, unassigned.

5. Remaining Effort — Corrected Summary

Known remaining (epics with estimates, corrected)

Epic Status Corrected Remaining Assignee
PLT-169 In Progress 1w Johan Ekman
PLT-2792 In Progress 2w (suggested) Bart De Boer
PLT-2478 In Progress 1.5w (suggested) Sreekanth S.
PLT-1870 Test 3d (suggested) Daniel P.
PLT-2336 In Progress 1w Sreekanth S.
PLT-2101 Selected 2d (+ reassign overhead) Saikiran on vacation
PLT-2118 Test 2d Bart De Boer
PLT-2353 In Progress 1w 1d Bart De Boer
PLT-2483 Ready 1d Johan Ekman
PLT-2496 Ready 1d Unassigned
PLT-2494 In Progress 3d Johan Ekman
PLT-2495 Selected 2d Unassigned
PLT-2492 In Progress 3d Bart De Boer
PLT-2488 Code Review 1d Unassigned
PLT-2714 Code Review 1d Unassigned
PLT-2354 In Progress 5w (corrected from 1w 2d) Daniel P.
PLT-2359 In Progress 1.5w (suggested) Bart De Boer
PLT-2966 Backlog 2w (suggested) Unassigned
PLT-2357 Selected 1w (suggested) Unassigned
PLT-2358 Selected 1w (suggested) Unassigned

Totals

Metric Value
Sum of all corrected remaining estimates (person-days) ~97 person-days
Parallelism factor (5 engineers working concurrently) ÷ 2–3×
Critical-path elapsed time (Daniel P. → PLT-2354 dominates) ~28 working days
Available working days (1 Jul → 23 Aug W34, full attendance) ~38 working days
Buffer ~10 days

Methodology: Raw person-day totals are not useful for deadline assessment because 5 engineers work in parallel. The critical path runs through Daniel Pettersson (PLT-2354 at 5w = 25d, plus PLT-1870 at 3d, plus Inc 2.2 validation gate at ~5d) = ~33 days. With aggressive overlap between PLT-2354 completion and validation start, the realistic elapsed minimum is ~28 days. This leaves ~10 days of buffer against the W34 target — tight but achievable with focused execution.


6. Per-Person Capacity Analysis

Person Epics Corrected Remaining Feasible in 32 days?
Bart De Boer PLT-2792 (2w), 2118 (2d), 2353 (1w 1d), 2492 (3d), 2359 (est. 1.5w) ~5.6w (~28d) Tight. PLT-2359 adds Phase 0 scope not originally planned.
Johan Ekman PLT-169 (1w), 2483 (1d), 2494 (3d) ~2w (~10d) Comfortable
Daniel Pettersson PLT-1870 (3d), 2354 (5w corrected) ~5.6w (~28d) Critical path. 28 of 38 available days. 10 days buffer. Manageable if focused.
Sreekanth S. PLT-2478 (1.5w), 2336 (1w) ~2.5w (~13d) Comfortable
Saikiran Katta PLT-2101 (2d, now in Inc 2.4) 2d + reassign overhead On vacation. PLT-2101 must be reassigned immediately — now on the Phase 0 critical path in M2.
Unassigned PLT-2496 (1d), 2495 (2d), 2488 (1d), 2714 (1d), 2966 (2w), 2357 (1w), 2358 (1w) ~24d total Critical. Inc 2.3 has 3 unassigned epics totalling ~4w. Needs owners this week.

Bart De Boer has the most load — 4 epics plus he's building PLT-2359 (Phase 2 ECC parity) in parallel. This workload is unsustainable for one person.

Daniel Pettersson is on the critical path. PLT-2354 alone consumes 28 of 38 available days. This leaves ~10 days buffer — manageable but requires disciplined execution and no additional scope creep.


7. Can Phase 0 Close by Week 34?

Verdict: Achievable with disciplined execution. ~10 days buffer on the critical path.

Three factors require active management:

  1. PLT-2354 corrected to 5w — Daniel Pettersson's critical path consumes 28 of 38 available days. The remaining ~10 days provide buffer for the validation gates in Inc 2.2 (Shadow Mode Completion) and Inc 2.3 (API Parity Validation).

  2. Unassigned epics are invisible work. PLT-2496, 2495, 2488, 2714 — four epics with no owners. Combined they represent ~5 days of work plus review cycles. Until owners are assigned, these don't move.

  3. PLT-2101 (Routing, Inc 2.4) is now on the Phase 0 critical path. Saikiran is on vacation. This must be reassigned immediately — it gates the M2 exit.

Realistic timeline with corrections (target end weeks)

Week Date Milestone / Increment Target
W28 Jul 7-11 Assign owners. Reassign PLT-2101. Set estimates. Initiate Inc 2.1.
W29 Jul 14-18 Inc 1.1 target. PLT-169 finishes. PLT-2792, 2478 close.
W30 Jul 21-25 Inc 2.1 target. Export pipes (2483, 2494, 2496, 2495) close. PLT-2354 skeleton phase begins.
W31 Jul 28-Aug 1 Inc 1.2 + M1 target. PLT-1870, 2336, 2118 close. PLT-2354 parallel run + parity validation phase.
W32 Aug 4-8 Inc 2.2 target. PLT-2354 multi-tenant phase + ECC rendering support (PLT-2359). Begin Inc 2.3.
W33 Aug 11-15 Inc 2.3 target. API parity validation. Buffer week for parity re-runs.
W34 Aug 17-23 Inc 2.4 + M2 + Phase 0 target. PLT-2101 routing. Final sign-off.

8. Immediate Actions Required

This Week (Week 27)

# Action Owner Impact
1 Correct PLT-2354 estimate to 5w in Jira Daniel P. / Lead Stops the program from operating on a 1w 2d fiction
2 Set estimates on all 11 unestimated epics Lead / epic owners Enables sprint planning. Use the suggestions in §4 as starting points.
3 Assign owners to unassigned epics (PLT-2496, 2495, 2488, 2714) Lead 5 days of work sitting idle
4 Reassign PLT-2101 — Saikiran is on vacation Lead 2d task. Sreekanth S. or someone with ingress/routing familiarity.
5 Relieve Bart De Boer — he owns 4 active epics + Phase 2 work Lead Spread PLT-2492 or PLT-2353 to another engineer
6 Assign owners to Inc 2.3 epics (PLT-2966, 2357, 2358) Lead 4w of API parity work; PLT-2966 is new and needs scoping. PLT-2357/2358 are Selected but unassigned.

Before Week 30

# Action
7 Run first 24h parity check on Replatforming-Dev as soon as PLT-2354 is skeleton-complete (Inc 2.2). Don't wait for all pipes to be perfect.
8 Confirm summer vacation schedules for all 5 engineers. Any additional time off in August further compresses the window.
9 If PLT-2354 is at risk of slipping past Week 32, consider parallelizing Inc 2.3 (API parity) with Inc 2.2 (Shadow Mode Completion) validation.

9. Risks Introduced by Estimate Gaps

Risk Severity Detail
Deadline set against fictional data 🔴 Critical The original mid-August target was agreed with PLT-2354 at 1w 2d. The corrected 5w estimate pushed the realistic close to Week 34. Stakeholders have been informed; the programme now targets Week 34 as the Phase 0 close.
Bart De Boer overload 🟡 High 6 epics across M1, M2, and M5. No single engineer can sustain this breadth. Risk of burnout + quality degradation.
Invisible validation gate 🟡 High Inc 2.3 now has three Jira epics (PLT-2966, 2357, 2358) but all are unassigned with no estimates. PLT-2966 is brand new — needs scoping before work can begin.
Summer vacation compression 🔴 High July–August is peak vacation season in Sweden. 32 working days assumes 100% attendance — an unrealistic assumption. Each week of vacation for Daniel P. or Bart adds 5 days to the critical path. Confirm vacation schedules immediately and rebaseline the timeline.
No buffer anywhere 🟡 Medium The corrected timeline has zero slack. Any bug, any parity failure, any sick day pushes the deadline.

10. Recommendations for Going Forward

  1. Treat PLT-2354 as the programme's heartbeat. It is not "an epic in M2 Inc 2.2" — it is the integration of everything Phase 0 produces. Give it the visibility and resourcing of a Milestone gate, not a feature ticket.

  2. Make estimates mandatory before sprint planning. 11 of 18 epics with no estimates is not a data gap — it's a planning failure. Every epic entering a sprint must have an original estimate. Retros should flag unestimated epics as process debt.

  3. Scope and assign Inc 2.3 epics. PLT-2966 (new), PLT-2357, and PLT-2358 now exist in Jira for API Parity Validation. PLT-2966 needs immediate scoping. All three need owners and estimates.

  4. Re-baseline the Phase 0 target date. With corrected estimates, the realistic close is late August (Week 34). Communicate this to stakeholders now, not in the first week of August when the slip is already visible.

  5. Track burndown against corrected estimates. Once all 18 epics have estimates, create a burndown chart from Week 27 to the target close. Update weekly in the status doc.


Companion docs: 15 — Overall Status (current epic states) · 19 — Delivery Framework (Phase → Milestone → Increment → Epic hierarchy) · 17 — Phase 1 Plan (what Phase 0 gates unlock)